PROPOSAL FOR REVIEW

PROJECT TITLE:

SRI LANKA:
RENEWABLE ENERGY AND CAPACITY BUILDING

GEF FOCAL AREA: CLIMATE CHANGE

GEF ELIGIBILITY: FCCC RATIFIED

23 NOVEMBER 1993

TOTAL PROJECT COSTS: $2,114,000

GEF FINANCING: $1,514,000

GOVERNMENT COUNTERPART FINANCING OF GEF COMPONENT: $200,000

COFINANCING/PARALLEL FINANCING: $400,000 /UNDP & OTHERS

ASSOCIATED PROJECT: NOT APPLICABLE

GEF OPERATIONAL FOCAL POINT: NOT AVAILABLE

GEF IMPLEMENTING AGENCY: UNDP

EXECUTING AGENCY: GOVERNMENT OF SRI LANKA, MINISTRY OF IRRIGATION, POWER AND ENERGY

LOCAL COUNTERPART AGENCIES: CEYLON ELECTRICITY BOARD; MINISTRY OF SCIENCE AND TECHNOLOGY; AND ENERGY CONSERVATION FUND

ESTIMATED APPROVAL DATE: JULY 1996

PROJECT DURATION: 3 YEARS

GEF PREPARATION COSTS: $18,000

SRI LANKA: RENEWABLE ENERGY AND BUILDING

BACKGROUND 1.

In 1994, Sri Lanka's population was estimated at 17.8 million inhabitants, about 80% of which were estimated to live in the rural areas. For 1993, GNP was approximately $10.1 billion, giving a GNP per capita of approximately $574. In 1993, agriculture was estimated to account for 21.3% of GDP.

2. Biomass continues to account for the largest fraction of Sri Lanka's primary energy supplies, and it is consumed largely in the domestic sector. Hydro is the next most significant primary resource with the 1400 MW of installed capacity generating more than 3500 GWh in 1992. The country imports more than 2000 million tons of oil and petroleum products primarily for the transport sector. To avoid a potential generating capacity gap, the Ceylon Electricity Board is considering the introduction of thermal power stations (diesel, coal and gas) totalling some 1300 MW capacity by 2010.

3. Significant parts of the country remain unelectrified and thus stand alone energy technologies are in demand. There are estimated to be more than 5000 solar (photovoltaic) home systems in use in the country, more than 20 village micro-hydro schemes and a few micro hydro and wind powered battery chargers (for charging automotive batteries used in households).

4. In October 1995 the Ceylon Electricity Board (CEB) approved the establishment of a Pre-Electrification Unit (PEU) to support the private sector and NGO developers of renewable energy schemes. In addition, the Ministry of Science and Technology has recently established an Alternative Energy Division. The National Engineering Research and Development (NERD) Centre has on-going solar, wind and micro-hydro R&D programmes. CISIR and the Universities are also active in some of these areas.

5. The World Bank has prepared an Energy Services Delivery (ESD) project for support from the IDA and GEF. The objectives of this project (to be appraised in July of 1997) are:
a) to encourage the participation of the private sector, NGOs and co-operatives to provide grid-connected and off-grid energy services with renewable energy technologies;
b) to design a Demand Side Management (DSM) strategy and
c) to strengthen the public and private institutional capacity on renewable energy and DSM.

There are three project components;
a) an ESD credit line to offer long term financing for renewable energy (with micro hydro and solar photovoltaic pilot projects);
b) a 3MW pilot wind farm and
c) technical assistance to support these and for DSM programme development. This project was designed in conjunction with the ESD project to enhance the effectiveness of the ESD project and to lay the foundation for future expansion of renewable energy exploitation in Sri Lanka.

Institutional Background

6. Since 1990, matters relating to the environment have been handled by the Ministry of Transport, the Environment and Women's Affairs. The environment division is the focal point for all matters relating to UN Framework Convention on Climate Change. A co-ordinating group on Climate Change has representatives from the Ministry of Irrigation, Power and Energy, Ministry of Science, Technology and Human Resources, Ministry of Agriculture, Lands and Forestry.

7. Under the auspices of the Ministry of Irrigation Power and Energy, the Ceylon Electricity Board is a key player in the Renewable Energy and Energy Efficiency sector.

8. In 1995, a National Committee for preparing a Sri Lanka Energy Policy was formed comprising 14 members representing the main ministries, petroleum corporation, Chamber of Commerce and individual experts. PROJECT OBJECTIVES9. The objective of the proposed project is to remove barriers to the expanded and sustainable utilization of renewable energy in Sri Lanka. The project will facilitate and accelerate the use of renewable energy technologies and energy efficiency measures in Sri Lanka thus reducing the need for additional fossil fuel thermal power stations and greenhouse gas (GHG) production (ie., CO2) associated with fossil fuel power stations and the decentralized use of kerosene and woodfuel. The project was designed as a technical assistance project to fit under GEF Climate Change Programme 2, Promoting the Adoption of Renewable Energy by Removing Barriers and Reducing Implementation Costs.

10. The project has been developed with the objectives of supporting activities which complement and enhance the World Bank/GEF Energy Services Delivery project. The project's design was finalized in conjunction with a joint programming mission undertaken between the World Bank ESD task managers and a UNDP consultant in October/November of 1995.

Barriers to the Expanded Use of Renewable Energy

11. This project is intended to remove three specific barriers to the expanded utilization of renewable energy in Sri Lanka. The first barrier is the limited information base about renewable resource potential, particularly in the case of wind, small hydro, and woody biomass resources. The second barrier is the limited familiarity with and confidence in the renewable energy technologies on behalf of both the private sector and consumers. The third barrier preventing widespread sustainable use of renewable energy is the shortage of skilled personnel trained in the techniques and practices relevant to the expanded use of renewable energy and enhanced energy efficiency.

12. The removal of these three barriers forms the basis for the objectives of this project. Under the three primary objectives of removing these barriers are grouped eight specific activities or project components intended to reduce the significance of those barriers.

PROJECT DESCRIPTION

13. As currently envisioned, the project will consist of eight activities in pursuit of removing the three barriers under the three objectives. The following section discusses each component of the proposed project. The discussion focuses on the objectives of the component, a description of the activity, justification, transaction barriers to be overcome, the proposed partners for implementing the activity and the anticipated outcome.

INSTITUTIONAL FRAMEWORK AND PROJECT IMPLEMENTATION 13.

The Ministry for Irrigation Power and Energy will be the executing agency with a Project Management Unit (PMU) within MOIPE or CEB (under the auspices of MOIPE). Project implementation will be managed as follows: Ceylon Electricity Board (under the auspices of the Ministry of Irrigation, Power and Energy) for Activities 1.1 and 1.2 (Wind monitoring and mini hydro resource identification) Alternative Energy Division of the Ministry of Science and Technology (for Activity 1.3 Biomass assessment, Activity 2.1 - Renewable Energy Certification with NERD, Activity 2.2- private sector mini-hydro capacity building, with NERD), Energy Conservation Fund (under the auspices of the Ministry of Irrigation Power and Energy) for Activity 3.3 (Renewable Energy technology promotion) and Activity 3.2 Energy Efficiency and Renewable Energy in the education sector). A Project Advisory Committee (PAC) would be drawn from:
Ministry of Power, Irrigation and Energy (Chair)
Alternative Energy Division of the Ministry of Science and Technology
Ministry of Transport Environment and Women's Affairs
Ministry of Agriculture (Forestry Planning Unit)
Ministry of Finance
Ceylon Electricity Board
Energy Conservation Fund
Sri Lanka Energy Manager's Association (SLEMA)
NERD
The Sri Lanka NGO Energy Forum and other NGO's
ITDG Sri Lanka
The University of Moratuwa

14. At the August 1995 Global Environment Facility Operations Committee meeting (GEFOP) it was agreed that the UNDP would work closely with the World Bank and Government of Sri Lanka (GOSL) to develop a Technical Assistance project that would complement the Energy Services Delivery (ESD) project in Sri Lanka to be partly funded by GEF and partly by UNDP (IPF), the GOSL and/or bilateral agencies. In light of the above a UNDP consultant joined an IDA team mission in Sri Lanka to identify components of the proposed TA project for possible UNDP/GEF funding. The proposed institutional framework thus takes into consideration the framework of the ESD project.

15. Technical assistance (TA) to support the ESD project directly is already being proposed in the IDA/GEF proposal in two main areas: (i). TA to the CEB's pre-Electrification Unit (PEU) to support private sector and NGO developers of renewable energy electricity service delivery schemes. The PEU will undertake feasibility studies, design reviews, testing and developing standards (ii). TA to the CEB's Demand Side Management (DSM) Unit for Load Research and in particular initially the development of a DSM Action Plan and DSM Load Research Programme Implementation plan

16. As part of the joint programming initiative in Sri Lanka, six elements of the UNDP initiative were meant to strengthen directly the World Bank ESD project, namely, Activities 1.3, 2.1, 2.2, 3.1, 3.2 and 3.3. Activity 1.3 will identify future biomass power installations which can be funded under the ESD project. Activities 2.1 and 2.2 should help secure the design of and standards for technologies involved in small hydro and other renewable energy investments. Activities 3.1, 3.2 and 3.3 are intended to strengthen the capabilities of Sri Lankan energy managers, architects and engineers and the public at large to avail themselves of the opportunities under the ESD project as well as increasing the pool of skilled Sri Lankans familiar with the new building codes and renewable energy. The remaining two elements of the project, Activity 1.1 and 1.2 are intended to the foundation for future renewable energy investments by providing more information about renewable resources.

17. It is not intended that all the objectives of the 12UNDP/Sri Lanka Renewable Energy project flow into the World Bank/Sri Lanka/ESD project. This is because the scope of the UNDP/Renewable Energy project is wider than the World Bank/ESD project, providing a supportive environment for development and dissemination of renewable energy technologies. Since the bulk of the Sri Lanka/World Bank/ESD project is provision of credit line to be administered by financial units, institutional strengthening for dissemination of renewable energy technologies through, for example, enlightened private sector energy managers, is expected to go a long way in establishing financial stability of the ESD credit line.

18. There are numerous participating agencies and stake holders in the Sri Lanka/UNDP Renewable Energy project. This reflects the varied range of activities the project is expected to cover in its attempt to create an overall environment for development and dissemination of renewable energy technologies in Sri Lanka. The World Bank/ESD project, on the other hand, has a single major partner agency i.e., the Ministry of Finance, through which it can access development banks and other administrative units. A co-ordinating mechanism is therefore expected to be set up to ensure operational complementarities between the two project activities.

CONSULTATIVE PROCESS

19. This project proposal was developed under a joint UNDP-World Bank mission in November 1995. Discussions were held with MOIPE, Ministry of Science and Technology, Ministry of Transport Environment and Women's Affairs, Ceylon Electricity Board, SLEMA, Energy Conservation Fund, Urban Development Authority, University of Morituwa, CISIR, NERD, SL Standards Institute, PV Industry (Exide Batteries and Power and Light) and NGO's (ITDG Sri Lanka and Solanka Associates). The proposal was also drafted in close co-operation with UNDP and World Bank representatives in Sri Lanka. Earlier drafts of the proposal were provided to the Sri Lankan participants for review.

NGO LIAISON

20. There is an NGO Energy Forum operating in Sri Lanka. Discussions were held with the Secretariat (ITDG Sri Lanka), with the principal micro hydro NGO (ITDG Sri Lanka) and one of the principal photovoltaic NGO's (Solanka). Their suggestion have been incorporated into the design of the current project, and several NGO's will be involved in project implementation.

MONITORING AND EVALUATION

21. Tripartite reviews will take place according to UNDP/GEF rules each year of the project. In addition, GEF will pay for additional technical consultants to attend the tripartite reviews and ensure adequate attention to project success. In addition, the monitoring of each individual activity will be supported as part of that activity.

SUSTAINABILITY

22. The project includes significant capacity building components and involves the key renewable energy and energy efficiency agencies working together. It is intended to create a more sustainable environment for renewable energy dissemination in Sri Lanka. Once the curricula are designed under Objective 3, they will be incorporated into the ongoing training and education programmes.

RATIONALE FOR GEF SUPPORT

23. This project is fully consistent with GEF objectives and has been prepared under the evolving guidelines for Climate Change Long-Term Operational Programme 2: Promoting the Adoption of Renewable Energy through Removing Barriers and Reducing Implementation Costs. The project will enable and assist in the development of wind, hydro and biomass technologies for grid connected power, PV for non-electrified areas and improve the capacity for implementing the use of low carbon energy sources as well as improve the efficiency in energy use.

INCREMENTAL COSTS

24. In the absence of this TA project, the development of wind, mini-hydro, PV and biomass technologies would develop more slowly in Sri Lanka and the disbursements under the ESD project would also be much slower. The incremental cost summary is presented in Annex 1.

PROJECT COSTS

25. The overall project cost is estimated as US$2.114 million summarised by component below:


Overall project Cost
Activity Total Cost
US$000
UNDP & Others
US$000
GoSL Cost
US$000
GEF
US$000
Activity 1.1 Wind Monitoring 380 70 30 280
Activity1.2 Mini Hydro Assessment 330 70 30 230
Activity 1.3 Dendro-thermal Power Assessment 300 70 30 200
Activity 2.1 Certification of Ren. Energy Equip. 250 -0- 30 220
Activity 2.2 Mini-Hydro Industrial Support 260 45 15 200
Activity 3.1 Energy Manager's Energy Eff. Training 140 125 15 -0-
Activity 3.2 R.E. and Energy Eff. in Education 330 20 45 265
Activity 3.3 R.E. Promotion Campaign 60 -0- 5 55
Subtotal 2,050 400 200 1,450
Monitoring/Evaluation 20 -0- -0- 20
Support Costs (3%) 44 -0- -0- 44
TOTAL 2,114 400 200 1,514

The basis of the costing is presented in Table 1.

PROJECT FINANCING

26. The Government of Sri Lanka (GoSL) will agree to co-financing of US$400,000 from either UNDP's IPF or the contribution of other donors. The GOSL itself will makes its own contribution of $200,000 in support of salaries of staff and other in-kind contributions. (See Table 1)

27. The GEF contribution sought is thus US$1.514m.

RISK ISSUES

28. The principal risk to the proposed project is that the capacity of the implementing institutions may not be sufficient to undertake or manage the proposed components of the project. This risk is highlighted with respect to the implementing institutions as follows:

Table 1. Component Cost Summary


Activity                    Project      SubcontractsCo Equipment +    Other       COMPONENT        
                            Staff        nsultants                                 COST             
                            US $ '000     US$' 000      US$ '000       US$ '000     US$ '000        

1.1  Wind Monitoring            60           75            150             95      380              

1.2 Small Hydro Assessment      60           75            105             90      330              

1.3 Biomass Assessment          60           75             75             90      300              

2.1  Certification of R.E.      60           40             100            50      250              
Equipment                                                                                           

2.2  Hydro Industry             30           75              50           105      260              
Strengthen.                                                                                         

3.1  Strengthening Private      30           25              65            20      140              
  Sector Energy Efficiency                                                                          

3.2  Energy Efficiency and  90           100              70             70        330              
R.E Education                                                                                       

3.3  R.E. Promotion              10          10              35           5         60              
Campaign                                                                                            

Subtotal                       400**     475               650           525       2,050            
                                                                                                    
Monitoring and Evaluation                                                             20            
                                                                                                    
Support Costs inc.                                                                                  
Executing Agency Costs                                                                44            
(3%)                                                                                                

TOTAL                                                                              2,114            



** The GoSL will finance 50% of Staff Costs.

ANNEX 1

CALCULATION OF INCREMENTAL COSTS

1. Broad Developmental GoalsSri Lanka is attempting to fulfill its energy needs for a largely rural population which currently uses mostly woodfuel and some kerosene for lighting. The bulk of the population has no access to electricity.

2. Baseline: Under the baseline, two courses of action could be envisioned. The first is that the current situation, with the rural population dependent upon traditional fuels supplemented by kerosene would continue to be the rule for the foreseeable future. While this might be considered to be likely, it is not clear that it is wholly environmentally sustainable, given the heavy dependence upon woodfuel. The second option sees a much heavier role for electrification drawing upon conventional fuels, large-scale hydropower and a very limited use of renewables. This second option is a more ambitious, development-oriented scenario, but it is not clear that it is financially viable. The actual baseline, without this project and the companion ESD project, is likely to fall somewhere in-between.

3. Global Environmental Objective: The global environmental objective being pursued in this project is the reduction of GHG's from the energy sector in accordance with the goals of the climate change convention.

4. GEF Alternatives The GEF alternative includes the activities described in the project brief, namely, increased renewable energy assessment, improved development of renewable energy technology capabilities, and increased information and training for both professionals working in the field and the general public. In the absence of the project, it is not clear that these activities would take place in a systematic and comprehensive manner without GEF support.

5. System Boundary For the sake of this discussion, the Sri Lanka energy system constitutes the boundary.

6. Additional Domestic Benefits: There will be considerable domestic benefits associated with the information, technological improvement and training components of this project. However, most of the costs are not immediately recoverable. Co-financing to cover these 'baseline costs' and benefits has been raised from both the UNDP/Others and other financiers and the GoSL.

In terms of additional domestic benefits, there will be a decrease in pollution from any fossil-fuel fired plants which are avoided or delayed. There will also be the potential for professionals trained in energy management to filter out of the renewable energy sector to other sectors of the economy. A third area of domestic benefits may come from any reduced pressure or rationalized pressure on Sri Lanka's forest resources.

7. Costs: The cost of the project activities are take to be approximately US$2.05 million. There are no hard and fast accounting rules that have been applied to estimate these figures as the baseline is not readily quantifiable. Nevertheless, baseline funding of US$600,000 has been committed. In addition, since Activity 3.1, Energy Manager's training can be considered an energy efficiency activity and therefore falling under GEF CC Programme 1, its entire costs are being met from the baseline or co-funding contribution so as not to confuse GEF's programmatic evaluation. In a similar manner, since Activity 3.3, Renewable Energy Promotion Campaign would not be undertaken without the need to support the ESD project, its costs are considered to be fully incremental.

8. Incremental Cost MatrixThe matrix is applied to the three transactions barriers described in Annex I-1.

9. Agreement: The GoSL has agreed with the financing arrangements presented in this document.

TABLE I-1 Assessment of Incremental Cost and Transactions Barriers


Transaction Barrier   Activity           GEF Cost  UNDP     GoSL     Total     Likely Incremental   How will activity    
                                         ($000)    Cost     Cost     Cost      Cost                 be replicable?       
                                                   ($000)   ($000)   ($000)                                              

Resource Assessments  1.1 Wind                                                                      With detailed        
Inadequate to         monitoring         280       70       30       380                            information bases    
Support Renewable                                                              Monitoring Costs     for wind, biomass,   
Energy Investments    1.2.  Small Hydro                                        are Positive--       and small hydro,     
                      Assessment         230       70       30       330                            individuals,         
                                                                               Follow-on            communities and      
                      1.3 Biomass                                              investments will be  firms can both make  
                      Assessment         200       70       30       300       negative or nearly   investment           
                                                                               so                   decisions and        
                                                                                                    obtain financing     

Limited                2.1                                                     Standards: positive  Standards            
Technological         Certification of   220       --0--    30       250       inc. cost for        strengthen           
Options, Experience   R.E. Equipment                                           consumer             confidence &         
and Infrastructure                                                             confidence;          willingness to       
                      2.2 Support to     200        45      15       260       Industry             invest;              
                      Small Hydro Ind.                                         strengthen:          Technological        
                                                                               positive, leading    assist increase      
                                                                               to neg inc. cost     options open in Sri  
                                                                               invest.              Lanka                

Shortage of           3.1  Private                                             Energy managers and  After project,       
Information in Hands  Sector Energy      -0-       125      15       140       professionals need   training programmes  
of Professionals and  Manager Trng.                                            better training to   will be folded into  
the General Public                                                             manage and utilize   existing curricula;  
                      3.2  Training for                                        improved energy                           
                      Energy Eff and     265       20       45       330       efficiency and       Information on ESD   
                      R.E.                                                     R.E.;  Public needs  project and Energy   
                                                                               information to be    Efficiency Fund      
                      3.3  RE Public                                           able to avail        will be revised and  
                      Promotion          55                    5     60        themselves of ESD    updated              
                      Campaign                                                 programme                                 



ANNEX 2

STAP REVIEWER'S COMMENTS

By: Sam Baldwin, National Renewable Energy Laboratory (NREL)

Per the fax dated Thursday, Jan. 4, to review the proposal Sri Lanka: Capacity building and Resource Assessments for Renewable Energy and Energy Efficiency.

1. Overall, the project seems to be appropriately focused, with high priority needs identified and reasonable approaches to meeting these needs outlined.

2. This project directly addresses concerns of the Climate Change Convention and national responses.

3. The general approach of the project is appropriate, with changes noted below.

4. Project objections are valid, well focused, and achievable, with changes noted below.

5. Although probably not appropriate in this document, additional information and analysis of potential renewable and energy efficiency markets may be needed.

6. The activities outlined are appropriate.

7. Funding levels for this round of activities is adequate.

8. The time frames listed are probably appropriate, although in general these programs tend to move more slowly than desired.

9. Additional Comments on each section follow:
National Wind Resource Assessment: Only grid-connected wind farms and isolated stand-alone systems are listed under "objectives." Potentially as important for Sri Lanka are wind systems for wind-diesel hybrid systems for village minigrids. Wind-electric pumpers may also be as good or better than standard wind mechanical pumpers.

Wind resource assessment is a key area for investment to prompt initial wind company interest, but it should be coupled with appropriate government supports, potentially including financial mechanisms to lower the barrier posed by the high capital cost per KWH generated for wind systems. Appropriate financial mechanisms can spur much of the needed wind resource assessment by private developers.

Note: The wind "description" was mostly missing from the text faxed to me.

Dendrothermal Power and Commercial Biomass: This is, as noted in the text, a very important area of work. As written, however, there seems to be some confusion. Under justification, the proposal notes that biomass is the principal energy resource of Sri Lanka. This is presumably for household cooking and will itself directly "reduce future needs for fossil fuel power generation" as written. The various relationships and specific focus of this activity need to be clarified and expanded here.

Renewable Energy Equipment Certification: These activities are going on widely and I am currently having discussions with the World Bank IENDP to standardize, for example, World Bank Procurement specifications for certain renewable systems. NREL is also working with several countries to train staff and help establish facilities for equipment testing and certification. It will be important that this component of the study be done in conjunction with the many other activities in this field to avoid duplication.

Strengthening Private Sector Energy Efficiency: Training is an important component of increasing the market penetration by efficient equipment, particulary for systems integration. Another, often more important effort that is not mentioned here is the establishment and validation of efficiency standards for manufactured equipment such as refrigerators, lights, motors, etc. The United States has established a variety of standards for different types of equipment, and it is recommended that U.S., European, and other standards be reviewed and appropriately modified and incorporated into the Sri Lankan context.

Renewable Energy Promotion: These activities should be centered on existing renewable energy efforts.

Energy in Education: As above, much has been done in this area and should be made use of. Along with training or perhaps in conjunction with training, model building designs should be developed that demonstrate the benefits and low cost of passive solar buildings. One of the more successful US programs has been to hold design competitions with small prizes and relatively broad criteria for winning so that a large number of architects/buildings receive prizes sufficient to cover most of the additional design work. This encourages architects to learn about renewables, applies the results to real world buildings, and can lead to model buildings with little cost to the government.

Missing from this proposal are two key items: market assessment and the creation of business infrastructure. A careful assessment of the various market segments is needed to encourage, if the potential market warrants it, private sector interest and investment; and to prioritize activities. As these activities will be largely creating a new industry in Sri Lanka, it may be necessary to also support the creation of a viable national industry for much of the work. This might include matchmaking with financial entities, business incubators, business training (not specifically renewables), and others.

NREL has considerable expertise in many of these areas; please let me know if we can be of assistance.

Annex 3


LETTER OF ENDORSEMENT DEPARTMENT OF EXTERNAL RESOURCES

Ministry of Finance,
Planning, Ethnic Affairs and National Integration The Secretariat,
3rd Floor PO Box 277,
Colombo 19 February 1996

Resident Representative
UNDP Office
Colombo, Sri Lanka

Dear Sir: SRI LANKA RENEWABLE ENERGY & CAPACITY BUILDING PROJECT

This refers to your letter dated 14th February 1996 on the above subject.We are pleased to inform you that we are in agreement with the project proposal. Further, we would like to inform you that the programme identified under the project are of high priority areas of the Power & Energy Sector in Sir Lanka and also this project will be complementary to the proposed Energy Services Delivery Project of the World Bank.I shall be grateful if you would kindly obtain the GEF financial facilities for the proposed project.

Yours faithfully,

N. Madanayake,

Director for DG/ERD cc: 1. S/Irrigation, Power & Energy 2. S./Science 7 Technology 3. DG/National Planning Dept.



WORK PROGRAM PROPOSED FOR COUNCIL APPROVAL

GEF/C.7

GEF Council Meetings

Return to GEF Home Page Menu