PROPOSAL FOR REVIEW

PROJECT TITLE: BRAZIL: BIOMASS POWER GENERATION: SUGAR CANE BAGASSE AND TRASH

GEF FOCAL AREA: Climate Change

GEF ELIGIBILITY: Under financial mechanism of Convention, Ratified 28 February 1994

TOTAL PROJECT COSTS: US$ 3.75 million

GEF FINANCING: US$ 3.75 million

GOVERNMENT COUNTERPART FINANCING OF GEF COMPONENT: not applicable

CO-FINANCING/PARALLEL FINANCING: US$2.767 million - COPERSUCAR (Private Sector)

ASSOCIATED PROJECT: BRA/92/G31 - Biomass Integrated Gasification - Gas Turbine

GEF OPERATIONAL FOCAL POINT: Mr. Roberto Jaguaribe - Secretary of International Affairs - Ministry of Planning and Budget

GEF IMPLEMENTING AGENCY: UNDP

EXECUTING AGENCY: Ministry of Science and Technology

LOCAL COUNTERPART AGENCY: Ministry of Planning and Budget

ESTIMATED APPROVAL DATE: June 1996

PROJECT DURATION: 2.5 years

GEF PREPARATIONS COSTS: none


BRAZIL: BIOMASS POWER GENERATION: SUGAR CANE BAGASSE AND TRASHGENERAL OBJECTIVE1. To determine the technical, economic and agronomic feasibility of the use of Biomass Integrated Gasification/ Gas Turbine (BIG/GT) technology for power generation, using bagasse and sugar cane trash as the primary fuels, and pave the way for the following investment phase targeting a wide scale replication and cost reduction of the technology. The project falls under the Operational Program 3 of the GEF Operational Strategy on the focal area of climate change, namely "Reducing the Long-Term Costs of Low Greenhouse Gas-Emitting Technologies"Specific Objectives: (a) To determine availability and volumes of bagasse/trash biomass for potential use in BIG/GT systems. (b) To determine the quality and costs of bagasse/trash biomass. (c) To evaluate economic and agronomic costs and benefits of trash substitution for herbicides, as a consequence of green cane harvesting. (d) To evaluate existing and emerging technologies for green cane harvesting. (e) To evaluate biomass gasification of bagasse/trash. (f) To define and model integration of the BIG/GT system with the sugar mill. (g) To disseminate project findings and information to the world's sugar cane producing countries.PROJECT SUMMARY 2. Biomass utilization for energy production, in substitution for fossil fuels, can make a substantial contribution to limiting CO2 accumulation. The use of biomass as fuel for electricity production in small-scale generation systems has technical and commercial potential, if modern conversion technology is employed. 3. Under this rationale, the Global Environment Facility approved funding during the Pilot Phase for the Biomass Integrated Gasification/Gas Turbine Project (to avoid confusion between the technology being developed/adapted in this project and the project itself, the project will be referred to hereafter as Biomass Power Generation - Woodchip Project or WBP). The aim of the WBP is to demonstrate the commercial viability of the use of woody biomass in developing countries as fuel for electricity production from BIG/GT technology. 4. The proposal described here is concerned with the technology development and research needed - in addition to, and building on, that of the WBP - to introduce the BIG/GT technology in the sugar industry in Brazil, using bagasse and sugar cane trash as the primary fuels, allowing the further replication and cost reduction of the technology through learning and economies of scale. The proposed project will analyze experience to date in the development and testing of technologies for gathering, storing and using sugar cane trash and residues in leading sugar producing countries, with especial attention to the GEF-financed project in Mauritius entitled Sugar Bio-Energy Technology. To hasten worldwide application of BIG/GT technology in the sugar industry, this project will disseminate its findings and reports to the world's more than eighty sugar producing countries by holding two separate workshops to discuss the focus and scope of the project as well as its final results. The project falls under the Operational Program 3 of the GEF Operational Strategy on the focal area of climate change, namely "Reducing the Long-Term Costs of Low Greenhouse Gas-Emitting Technologies"5. The progress and momentum of the GEF-financed WBP provide an exceptional foundation, as well as opportunity, for the extension of the project to another geographically widespread source of plentiful, low-cost biomass with potentially significant effects on the global carbon cycle. This project will take advantage of the work already accomplished or underway in gas turbine development in the WBP and will build directly on bagasse gasification assessments by GE and others, including preliminary evaluations by contractors in the WBP. 6. This project will work closely with the WBP to ensure that technology development is responsive to the specific requirements of bagasse and trash as fuel. Timely GEF funding of this project is necessary to build on the momentum achieved under the WBP as well as to take advantage of the ongoing development of related agricultural technologies and systems around the world in the context of southern Brazil's cane growing season. Delay in funding this initiative would result in unnecessary duplication of WBP-related activities at a later date, at what could conceivably be a higher cost. Background Biomass Energy; Biomass Power Generation; Sugar Cane7. Biomass utilization for energy production, as a substitute for fossil fuels, can make a substantial contribution to limiting CO2 accumulation. Global biomass production today is 120 billion tones of dry mass per year, with an energy content equivalent to over five times the present world energy demand; however, the ten percent of world's primary energy input due to biomass are provided, usually, in very inefficient ways.8. The use of energy plantations (as in the WBP) or biomass residues (as in the sugar cane industry) as primary energy sources for electricity generation, with the most efficient technology, could have a significant impact on reducing CO2 accumulation.9. In 1990 sugar cane production reached 1.03 x 109 metric tons, on 16.9 x 106 ha, worldwide, in more than 50 countries. The corresponding bagasse production is 0.29 x 109 metric tons at 50% moisture, equivalent to 50 x 106 tons of fuel oil. This extraordinary amount of renewable fuel is concentrated at the sugar mills and is almost entirely used for energy generation at very low efficiency levels to produce sugar and ethanol (approx. 15%). The low or null opportunity cost provides little incentive for efficient utilization.10. Sugar cane production has been increasing at a rate of 2.3% per year over the last years. At the same time, the general practice of burning sugar cane fields to permit simpler harvesting operations has been subject to growing criticism on environmental and health grounds; this will lead increasingly to the practice of green cane harvesting. Green cane harvesting leaves large amounts of trash (sugar cane dry and green leaves, and tops) for energy purposes; estimates vary from 0.10 to 0.18 tons dry mass/clean stalks fresh mass, for commercial sugar cane. Conservatively it may be assumed that it is possible to double the amount of this biomass at the sugar mill. One estimate indicates that bagasse and trash could reach the equivalent of 100 x 106 tons of fuel oil, at present worldwide production rates. 11. Today the substitution of bagasse for fossil fuel as the primary energy input to sugar manufacture and the limited production of cogenerated electricity (usually in low efficiency, low temperature Rankine cycles) represents the sugar industry's contribution to the reduction of CO2 emissions. In Brazil, taking into account the effect of ethanol utilization, the net CO2 savings in emissions from the cane industry overall accounts for as much as 18% of the country's total emissions from fossil fuels.12. Results of the studies leading up to the formulation of this proposal have been extensively discussed by the sugar cane industry and the state-owned electric power system. Proposed legislation to promote cogeneration by the private sector is being analyzed by Congress. In particular, in the state of Sao Paulo, an agreement is under discussion among sugar mill owners, the State's Secretary of Energy and public utilities to promote increased power production at the sugar mills. 13. New and emerging technologies for efficient conversion of bagasse and trash to electrical energy can make a significant contribution worldwide to the reduction of CO2 accumulation. Detailed evaluations of conventional (steam based) power cycles for use in Brazilian sugar and ethanol mills indicate the possibility of increasing the usual level of 4% conversion (bagasse to electricity; cogeneration) to 16% or slightly more, including yeararound operation with cane trash. Hypothetical BIG/STIG systems could achieve at least 27%. Power production potential could represent a substantial portion of total current electricity production. JUSTIFICATION The Available Industrial Technology14. To increase the role of biomass for electric power production to significant levels it will be necessary to have either (or both) higher efficiency-low capacity (15 50 Mwe) cycles or very low cost, abundant sources of biomass. This requirement points to the use of BIG/GT systems fueled from energy plantations or agricultural residues.15. An extensive study was made, in preparation for this proposal, of existing cogeneration systems in Brazilian sugar mills; a sample of 42 sugar mills was made (of 400 currently in Brazil, processing 220 x 106 tons of sugar cane, nearly 20% of global production). Efficiencies were examined of steamraising bagasse boilers and steam turbine conversion to mechanical power or electricity, as well as process steam consumption. The optimal configuration of existing technology, with associated costs for retrofitting or substitution, were evaluated for all main items (boilers, turbines, generators, process steam consumption). Timeout statistics at the mill power station were analyzed; management techniques and bagasse storage systems were evaluated.16. The study's main conclusion was that conventional co-generation schemes with steam turbines can be greatly improved if the purchasing price of electricity is raised to the avoided cost for the integrated hydroelectric system. However, green cane harvesting with trash recovery could lead to a much higher level of power production and quality, allowing yeararound operation with biomass fuels. Development of this technology is also necessary to achieve lower costs with the BIG/GT technology, when much higher outputs would be reached.17. The BIG/GT concept, growing out of the work on IGCC (integrated coal gasification/combined cycle powers generation) for biomass utilization, points to the potential for high efficiency at the low power range, associated with possible low cost. Technology options to be considered in this context include: (a) Industrial or aeroderivative gas turbines (b) Atmospheric or pressurized gasification (c) Combined cycles or steaminjection cycles (also, cogeneration)18. The GEF-financed WBP program now underway is currently examining these options. 19. Effective integration of the sugar mill and BIG/GT system will require analysis of the following alternatives: (a) Independent mode (surplus bagasse trash used as fuel for an independent BIG/GT system). (b) Fully integrated mode (all bagasse/trash is gasified; steam from heatrecovery boiler is used for process in season). (c) Partial integration mode (some of the bagasse trash fueling through conventional boilers, providing a portion of the steam/power needs for the sugar mill).20. The last option can lead to a much simpler (nointerference) handling of the combined energy system, with an intermediate overall conversion efficiency (conversion would be maximized with the fully integrated mode). Preliminary analyses for sugar mills with capacities of 1 to 3 x 106 tons of sugar cane/year, in the three modes of operation, were performed. Power outputs and associated costs were evaluated. Ratios of conversion (biomass to electric energy) ranged from 21% (independent mode) to 36% (fully integrated, cogeneration).21. Bagasse and trash gasification would require further analysis (beyond that required for woodchips in the WBP) on some specific issues: (a) The feeding of loose material; the high specific volume would make utilization of feeders tested for woodchips difficult; the problem might be considerably more important for pressurized systems. (b) The possibility of higher alkali levels in the green portions of trash, leading to lower sintering points for ash in gasifiers. Again, pressurized gasifiers (in principle, requiring higher temperatures) would pose special problems. (c) Bagasse drying technology, both steambased or heated air (flue gas) -based systems, is sufficiently known. Best options would be to the BIG/GT/sugar mill integration studies; the use of a complementary autonomousdrying system is probably required since the moisture in bagasse trash varies significantly.22. Gas turbine options and development needed are exactly the same as for woodchipbased gas, and no further problems are expected after gas cleanup. Available and Emerging Agricultural Technology23. Harvesting, loading and transportation account for 34% of the raw material (sugar cane) costs in Brazil. Most common systems in use today consist of preburning, manual harvest (only 10% mechanized), and mechanical loading on trucks for transportation to the mill. Mechanical harvest in done either with chopped or whole sugar cane.24. It is expected that environmental legislation will continue to lead towards green cane harvesting. One of the main objectives of the preparatory work for this proposal was to identify options for promising green cane harvesting systems. The search for costeffective systems considers the full use of trash; utilization for energy (electric power, fuel oil substitution or even ethanol from hydrolysis) could potentially pay for the added cost of green cane harvesting and trash recovery. 25. A detailed evaluation was carried out of possible alternatives, using the bestavailable information on existing equipment, and extrapolating (in some cases) performances measured in experiments with new machinery, mainly at Copersucar. Results led to the selection of four alternatives for whole and chopped green cane harvest, handling and transport.26. Performance standards (i.e. final sugar cane quality, level of impurities and losses) and costs for equipment in each alternative were established. Some of the alternatives employ recently developed equipment (i.e. rotary push piler, cane transporter). Development requirements were identified for equipment in prototype stage to redirect it to green cane harvest (i.e. whole cane tworow harvester, cleaning station). As well, evaluation of baling equipment for sugar cane trash is required. Trash quality 27. Common calculations in Brazil indicate that about 10% (dry mass) of the stalk mass (whole stalk) is trash, a significant amount, considering that bagasse (dry mass) is 12.5% of whole stalk mass. Experimental results worldwide vary from 9% to 28%. A more precise estimate of trash mass is essential for the economic analysis of the integrated BIG/GT/sugar mill system. 28. Trash quality (mainly alkali levels) may be a decisive factor for its utilization in BIG/GT systems. For this report, experiments were conducted showing that total alkali in the green portions of trash could reach up to 10 times the values found in bagasse; however values for dry leaves (a major constituent) were equivalent to those in bagasse. Average humidity is fairly uniform (50%). As mentioned above, precise knowledge of alkali levels will be helpful in determining gasifier type.29. Preliminary research was carried out on the possibility of using trash left on site as a weed suppressant, leading to a reduction in the use of herbicides and associated costs. Even with 67% of the trash removed, a reduction of nearly 80% of weed infestation was observed. The optimum range of percentages of trash left in soil would be determined by the savings from avoided herbicide utilization as compared to the value of trash as fuel. Preliminary Cost Evaluation for Recovered Trash and Electric Energy30. A preliminary analysis of return on investment was performed on an integrated BIG/GT-sugar mill system to verify: (a) The economic aspects of unburnt sugar cane harvesting and the trash costs associated with each of the technical alternatives identified above. (b) The energy price required for each technical alternative based on the export of surplus electrical energy. 31. Results are based on expected performances of several equipment items and processes; many other assumptions were made.32. Included among many factors for the trash costs were the following: (a) The effect of vegetal impurities on sugar cane milling (for each alternative). (b) Possible elimination of trash raking and herbicide application, depending on the trash blanket left in field. (c) Cane losses in the harvest (each alternative) and options for trash recovery.33. Eight alternatives were considered for unburnt whole or chopped cane, and costs were compared to a baseline representing current procedures in the most developed (lower cane cost) region in Brazil.34. Results are very promising; some alternatives show that the total cost for harvesting and transporting unburnt sugar cane + trash to the mill is lower than the cost today for harvesting and transporting burnt sugar cane (without trash). This is due to the much higher productivity (costeffectiveness) of prototype equipment as well as its performance with respect to cane quality (sugar cane dry cleaning avoids losses in washing cane, etc.). At least two alternatives were identified for follow-up research. Electric energy generation cost35. Plant configurations considered in the BIG/GT/sugar mill integration studies were analyzed for the three operating modes (independent, full cogeneration, partial cogeneration). All relevant investment (reducing energy and process steam consumption; storage areas; bagasse and trash reclaiming systems, auxiliary steam systems; BIG/GT system) were taken into account. Biomass availability (bagasse and trash) was determined and biomass costs were taken to be at least the opportunity cost (whenever the reclaiming trash cost was higher, the higher value was considered).36. From the set of 24 results (8 alternatives, 3 operational modes), some important considerations can be made. Coupled with the previous section on trash cost, those considerations are: (a) In determining trash cost, the effect of the vegetal impurity on cane crushing capacities and sugar losses must be considered in addition to the costs of collecting, transporting and processing the trash. (b) Trash costs depend strongly, as expected, on the sugar cane harvesting system. The alternatives studied present a range of trash costs (50% moisture) from US$ 4.00/t (opportunity cost) to US$ 24.60/t (chopped unburnt sugar cane and trash baling compared with whole unburnt sugar cane and transporting/ processing the trash together with the sugar cane. (c) The use of a BIG/GT system integrated in a sugar and alcohol mill, with varying load factors, derating and rates of interest, would lead to energy costs as shown below.


 Case                   Derating/                Electric energy costs    
                        interest rate/          (US$/Mwh)- excl state     
                        load factor             tax                       
 
1. Independent BIG/GT   Derating 20%/ 12%        73-77                    
combined cycle          interest/ 80% load                                
operation (I)           factor                                            
 
2. BIG/GT in full       No derating/             59-63                    
cogeneration mode (C)   12% interest/                                     
                        85% load factor                                   
 
3. BIG/GT in partial    No derating/             44-46                    
cogeneration mode (P)   8% interest/                                      
                        85% load factor                                   
 
 

37. Assumptions in Case 1 are, by design, conservative. A load factor of 85% is commercially feasible. Interest rates depend on prevailing economic situations and cost of capital at local levels. Results of the WBP, to date, indicate turbine derating to be unnecessary. Through learning about the technology and through replication, the set up of the plant will be optimized and performance improved , thus leading to further cost reductions.38. The very low relative cost of fuel (trash and bagasse) reflects the actual (and estimated future) situation in Brazil if the technologies under consideration for cane harvesting are successful. It must be noted that this situation (i.e., very high capital costs as compared to fuel costs even for a BIG/GT system) is different from those for other thermal systems (even the woodchip BIG/GT system). Some implications are clear; for instance, small gains in efficiency for thermomechanical conversion (pressurized systems and more advanced technologies) may become difficult to justify.Proposed Development Program: Objectives and Activities Objectives 1 and 239. To determine availability and volumes of bagasse/trash biomass for potential use in BIG/GT systems and to determine the quality and costs of bagasse/trash biomass. (a) Complete studies on trash availability and quality (Copersucar). Objective 340. To evaluate economic and agronomic costs and benefits of trash substitution for herbicides, as a consequence of green cane harvesting. (a) Complete studies on herbicide reduction with cane trash blanket management (Copersucar). Objective 441. To evaluate existing and emerging technologies for green cane harvesting. (a) Complete the development of new equipment for green cane harvest and handling (Copersucar): (i) Copersucar whole stalk harvester and sugar cane dry cleaning station. (ii) Test and improve largesize balers. (iii) Test comparatively, in green cane harvesting, existing equipment. (iv) Evaluate the selected four alternatives (sugar cane final quality, trash recovery and costs). (b) Environmental Impact Assessment of proposed green cane system on agroecosystem (i) Studies on effect of green cane harvesting system on soil biota, nutrient recycling, soil structure. Objective 541. To evaluate biomass gasification of bagasse/trash. (a) Gasification tests (i) Atmospheric gasification and gas cleanup (TPS). (ii) Pressurized gasification and gas cleanup (Bioflow). Depending on results from scoping tests (bagasse and trash) and engineering evaluation of bagasse feeding costs, full gasification tests in the Varnamo plant will be performed. Objective 6 42. To define and model integration of the BIG/GT system with the sugar mill. (a) BIG/GT Sugar mill integration analysis (i) Atmospheric gasification (Copersucar + TPS); (ii) Pressurized gasification (Copersucar + Bioflow); (iii) Final economic analysis (Copersucar).43. The previous experience with the BIG/GT has made it possible for Copersucar to prepare this proposal with a high level of detail regarding obligations and costs. The selection of companies for equipment/process test and development, following the steps of the ongoing WBP to avoid unnecessary costs, has resulted in the two gasifiergas clean up teams (TPS and Bioflow); and Copersucar proposes its own Technology Center as the leader for the work in Green Cane Harvesting and Fuel Availability, and the engineering integration with the sugar mill. Objective 744. To disseminate project findings and information to the world's sugar cane producing countries. (a) Development of an information dissemination strategy (b) Production of informational materials e.g., pamphlets, videos, etc., (c) Selected media campaigns in national and international journals and periodicals (d) Workshops: one workshop to inform interested public and private sector sugar cane producers of the scope and intent of the project; one workshop to inform of the results of the project.Implementation Arrangements 45. A simple management structure is proposed, based on the existing structure for the WBP program. The system must be able to reach the proposed objectives and ensure the proper controls to administer GEF funds efficiently.46. Strong interaction with the WBP program is essential; in principle, this project should be seen as an extension of the WBP. The scope of this extension is, however, simpler, not including phases beyond the technology development. It is not necessary, at this point, to consider a structure that will conduct commercial implementation of a pilot plant.47. The management structure of the project is outlined in the Annex to this brief. The Brazilian Government, through the Ministry of Science and Technology (MST), will be responsible to the GEF Implementing Agency for compliance with the obligations regarding the execution of this project. The MST will be the recipient of the grant from GEF to be held in a "Lock Box" account; disbursements will be recommended by a Management Committee" (MC). The MC will be comprised of representatives of MST, Copersucar and the ongoing WBP programme. 48. Detailed timetables for all project activities have been proposed. They are two main considerations: (a) A large portion of the experimental work on green cane harvesting can only be performed during the harvesting season (6 months/year, May to November). (b) Gasification tests will match the experiments with woodchips for the BIG/GT, usually following the WBP experiments, to take full advantage of the knowledge and experience acquired there.Incremental Costs49. As this project will lead to the extension of BIG/GT application to sugar industry, it will have significant implications for the rest of the world. As currently designed, the entire project is incremental in nature, as it would not be undertaken without GEF support. Baseline Situation:50. This project builds upon the earlier BIG/GT project being supported by GEF which links biomass gasification to the generation of electricity, making use of biomass integrated gas turbines. Since this activity is already being supported by GEF, it already forms part of the baseline. In addition, Copersucar will be spending $2.8 million to redesign and obtain new harvesting machinery. The project supplements these initiatives to make sure that the machinery can be used to obtain both the cane and trash for use in gasification.51. There will be no project-relevant national or global benefits in the baseline situation. Project Case:52. In this project, Copersucar is already advancing in the development of new green cane harvesting equipment. However, the project investment of $3.75 million is required to ensure that this machinery fits the specifications required to get the additional global benefits from gasifying the bagasse and trash. The incremental cost equals the project cost of $3.75 million. The project will enable Brazil (and the rest of the world) to generate large quantities of electricity through making efficient use of bagasse and trash which are currently wasted. On a global level, if Brazil builds one power plant to operate using bagasse and cane trash, the reduction in carbon emissions will fall between 177 and 412 tonnes of CO2 per annum (depending upon the assumptions used). For the rest of the world, the potential reduction in CO2 could range between 0.86 and 2.0 billion tonnes per annum if bagasse is used to displace fossil-fuel generated electricity. Budget53. The Budget includes funding required for development work at Bioflow, TPS, and Copersucar as well as funding for the administrative and managerial activities of the Management Committee (costs of fuel and shipment for gasification tests, traveling etc.).54. Copersucar is investing an amount of US$ 2,767,100 over two years (May 1993 April 1995) on programs for cane harvesting development and cogeneration technology improvement in sugar mills. This does not include the cost of prototypes (a few million dollars) and the specific expenses of 6 sugar mills involved in the program (personnel and equipment). The additional funding required for Copersucar for this project covers expenses specifically related to trash recovery, and integration of BIG/GT systems with the sugar mill. PROJECT BUDGET: FUNDING REQUIREMENTS


 Item                              Responsible                  Description                     Cost           
                                                                                                ( US$)         
 
Unburnt cane harvesting:                                       Mechanical components            5,000          
Equipment Development & Field                                  Engineering development:         87,500         
Testing                           Copersucar                   Personnel                                       
                                                               Material Analyses (30)            4,500         
Equipment Development                                          Development and Testing:           257,800      
 Whole cane harvester                                          Personnel                            1,000      
 Cane Cleaning Station                                         Phase 1: Transportation              5,000      
 Baler Studies                                                          Testing: Personnel                     
                                                               Phase 2: Baler cost               80,000        
                                                                        Testing: Personnel                     
Field test of agronomic routes                                                                  23,200         
                                                               Transportation costs                            
                                                               Maintenance costs                   12,000      
                                                               Personnel                           11,000      
                                                                                                  170,500      
 
Studies: Herbicide reduction      Copersucar                   Personnel                        56,700         
with trash use                                                                                                 
 
Studies: Trash availability       Copersucar                                                                   
and quality                                                                                                    
 Trash availability                                            Personnel and analyses           18,900         
 Trash quality                                                 Personnel and analyses              16,800      
 
Gasification Tests                                                                                             
  Atmospheric gasification and    TPS                          Total cost (estimated)             650,000      
gas clean-up                                                                                                   
 Pressurized gasification and     Bioflow                      Scoping tests*                     350,000      
gas clean-up                                                                                                   
                                                                                                               
Gasification and feeder tests     Bioflow                      Total cost (estimated): Pilot    670,000        
                                                               plant test                                      
 
BIG/GT Integration Analyses                                                                                    
 Atmospheric gasification system  TPS                          Gasification: information for    190,000        
 TPS tasks                                                     process and                                     
                                                               basic engineering                               
 Pressurized gasification system  Bioflow                                                                      
 Bioflow tasks                                                 Gasification: information for    190,000        
                                                               process and                                     
 Integration Analyses and         Copersucar                   basic engineering                               
 Final economic analyses                                                                          380,200      
                                                               Plant integration analyses                      
                                                               (both systems);                                 
                                                               includes cost assessments and                   
                                                               economic analyses                               
 
Dissemination workshops           Copersucar                   One workshop to inform           100,000        
                                                               interested public and private                   
                                                               sector sugar cane producers of                  
                                                               the scope and intent of the                     
                                                               project; one workshop to                        
                                                               inform of the results of the                    
                                                               project.                                        
 
Environmental Impact Assessment   Copersucar                   Studies on effect of green       250,000        
of proposed green cane system on                               cane harvesting system on soil                  
agroecosystem function                                         biota, nutrient cycling, soil                   
                                                               structure, etc.                                 
 
Miscellaneous / Contingency       Management Committee         Bagasse supplies to                 162,000     
                                                               gasification tests                              
                                                               in Sweden                                       
                                                                                                  50,000       
                                                               Other                                           
 
 TOTAL                                                                                           3'742,100     
 
 

* The work of Bioflow will follow a step-by-step approach as follows: scoping gasification tests are performed and evaluated with respect to using bagasse and trash as fuels; a feasibility study and test of transportation, handling and feeding of these fuels is carried out in parallel. Only if the outcome of these activities is encouraging, the following will be performed: process engineering and preliminary basic engineering (US$ 190,000), and feeder and gasification tests (US$ 670,000). If the outcome is unfavorable, the funds allocated to these budget lines (total US$ 860,000) will be reverted to the GEF. CALCULATION OF INCREMENTAL COST Costs National Benefits Global Benefits


Baseline         0 Project Cost       -----                          -------                             
                 $2.767 m                                                                                
                 Copersucar Cost                                                                         
 
Project Case     $3.5 m Project Cost  For Brazil:  Potential to use  For Brazil:  With one BIG/GT        
                 $2.767 m Copersucar  bagasse/trash to generate up   plant, between 177 and 412 * 103 t  
                 Cost                 to 628*103 GWH/annum           CO2  avoided                        
                                                                                                         
                                      For Rest of World:  Up to      For Rest of World:  Up to 2*109 t   
                                      2*106 GWH/annum                CO2 can be avoided annually         
                                                                                                         
 
Increment        US$ 3.5*106          Massive Potential for          Enormous Potential for CO2          
                                      Sustainable Power Generation   avoidance                           
 
 

LETTER OF COUNTRY ENDORSEMENT TECHNICAL REVIEW BRAZIL BIOMASS POWER GENERATION: SUGAR CANE BAGASSE AND TRASH OVERALL TECHNICAL FEASIBILITY OF THE TECHNOLOGIES OR SYSTEMS PROPOSED1. The proposed project is primarily a technology development effort having two relatively distinct parts: (1) industrial technology development, referring to equipment for the processing of sugarcane and for the efficient conversion of bagasse and cane trash into electricity, and (2) agronomic technology development, referring to methods for effectively harvesting and cleaning green cane to make cane trash available as a power plant fuel. Also proposed are some field measurements intended to establish the effectiveness of using a blanket of trash as an herbicide substitute and to determine accurately the quantities of trash that could be made available to a power generation facility. There are good overall prospects for successful technology development in both the industrial and agronomic areas. 2. The industrial technology development effort would be closely linked to the GEF's Brazilian biomass gas turbine demonstration project (the WBP). The WBP is the largest of about a half-dozen substantial biomass-gasifier/gas turbine (BIG/GT) development/ demonstration efforts ongoing worldwide. Construction of the first complete BIG/GT facility (a cogeneration facility generating 6 MWe and 9 MWheat) was finished early this year (in Sweden), and preliminary shakedown testing is ongoing. Full-plant testing is scheduled to begin by the fourth quarter of this year. The work proposed by Copersucar should make uniquely important contributions to the development of BIG/GT technology for applications with cane residues, but the overall success of the BIG/GT technology development effort will depend at least as much on the success of the WBP and the other ongoing demonstration efforts.3. The agronomic technology development effort would build significantly on earlier technology development work in Brazil (especially at Copersucar), and would also draw extensively on commercially established cane de-trashing technology developed in Cuba. The Cuban sugar industry uses some 900 "cane cleaning" stations to strip and separate trash from sugarcane that is cut green (without pre-burning the fields). The majority of Cuba's sugar cane (80 million tonnes total annual production capacity) is machine cut and cleaned. Thus, while the green cutting of cane is not practiced to any significant extent in Brazil today, the fact that systems for doing so are successfully operating elsewhere suggests that the prospects are good for developing such systems in Brazil, especially given Copersucar's capabilities and commitment to doing so.FEASIBILITY OF THE PROJECT'S PROPOSED DESIGN AND EXECUTION 4. The proposal appears well designed, insofar as technology development aspects are concerned. There has been substantial preliminary work done (especially in agronomic areas), on the basis of which Copersucar has prepared detailed descriptions of the work needed. The proposal is particularly well designed in that in both the industrial and agronomic areas, a set of alternative approaches are identified, and within each approach are branch points. For example, on the industrial side, the approach will be to consider both of the gasifiers being considered for the WBP, even though the atmospheric pressure system would appear to have some advantages. The proposal builds in a decision point after relatively inexpensive laboratory-scale tests to determine whether to proceed with larger-scale tests (and incure more substantial costs) with the pressurized system. This proposal design lends confidence that the work will be able to identify a range of feasible technological solutions, both industrial and agronomic.5. One item to note regarding project design is that the agronomic activities are largely constrained by the dates of the harvest season (Nov. - May). If tests are not completed during this window of opportunity, the project could be delayed considerably.DEMONSTRATION VALUE AND POTENTIAL FOR REPLICATION IN OTHER REGIONS OF BRAZIL AND THE DEVELOPING WORLD 6. It would be difficult to overstate the demonstration value of the proposed project. There are approximately 80 developing countries with substantial sugarcane-based industries, all of which stand to benefit from a successful technology development effort along the lines proposed by Copersucar. 7. The case may be overstated for potential power generation in some countries, e.g. island countries where land may be limited for further planting of sugarcane. Even in these countries, however, the application of BIG/GT systems could significantly enhance the national supply of electric power. For example, Cuba has a present sugarcane production capacity of about 80 million tonnes of cane. If Cuba produces this much cane, its sugar industry could generate close to 40,000 GWh/year from cane residues using first-generation BIG/GT technology. For comparison, the Cuban electric utility system generates 10,000 GWh/year (or less) today, almost exclusively from imported oil. Cuban sugar factories export a small amount of power (about 70 GWh/year) to the grid. 8. The potential for replication of the project in and out of Brazil is high for the industrial aspects. Agronomic replicability may be somewhat more problematic because of the fact that there are many different "cane cultures" in different countries and even within different regions of Brazil (especially the Northeast versus the Southeast). Harvesting and transporting systems range from highly mechanized--as in Cuba with its machine harvesters, trash cleaning stations, and dedicated rail system for transport to the mills--to highly manual systems--such as India, where hand cutting and bullock-cart transport of cane to the mills is not uncommmon. Given this, the agronomic adaptations that Copersucar is considering may be less effective in other cultural contexts. Nevertheless, Copersucar plans to try a number of alternative approaches, and different elements from different approaches may be workable in other contexts. In any case, it would be important to document well in the agronomic area, what worked and what didn't work. It will also be important to communicate this information to those presently operating different agronomic systems from those in Southeast Brazil. ECONOMIC AND INSTITUTIONAL FACTORS REQUIRED TO ENSURE SUSTAINABILITY 9. A key issue to insure the economic and institutional viability of cane-powered BIG/GT systems is that cogenerators be paid the full avoided cost (including both energy and capacity credits) for electricity sold to the grid. The equivalent of the United States' PURPA legislation (Public Utility Regulatory Policies Act) is needed in Brazil and many other cane growing countries to encourage the needed private investment in cane power. Private investors are likely to be hesitant to act without such legislation.10. The proposal shows estimates of the electric energy prices required to achieve real internal rates of return of 12% for different BIG/GT power generation alternatives (Table 21, p. 80). The prices estimated there are high compared to long-run marginal costs for new electricity supply in Brazil. If the assumptions behind these calculations are borne out in practice, the BIG/GT idea does not look economically sustainable, even with a PURPA-type legislation in place. 11. However, three of the key assumptions used in the calculations should be reconsidered, as a result of which required electricity prices will be such that the cane-BIG/GT systems will clearly be economically viable. First, the proposal calculations assumed a 20% derating of the gas turbine output based on the best available knowledge at the time. Recently developed information in the WBP project indicates that essentially no derating is required. Second, the load factor of 80% assumed in the proposal seems very conservative. The WBP project foresees a load factor of 85% for wood-fired BIG/GT plants, and industrial facilities typically operate with load factors of 90% or higher. Third, the 12% real rate of return required is artificially high by most investment standards. This value may have been selected to allow for high inflation rates in Brazil. Under "normal" conditions, a real return of 8% would be reasonable, as has been used in the WBP calculations.INCORPORATION OF RELEVANT STAKEHOLDERS INTO THE DESIGN AND EXECUTION OF THE PROJECT 12. The primary direct stakeholders in this project include the sugar industry in Southeast Brazil, which stands to gain an understanding of technology that will help generate a substantial new revenue source, and the people of Brazil, who stand to see expanded renewable electricity supplies and attendent environmental benefits like reduced burning of cane fields. The sugar industries outside of the Southeast of Brazil (including the Northeast Brazilian industry and those in other countries) are not explicitly involved in the project as presently conceived. In this regard, I would recommend an important addition to the proposal: a mechanism to insure that knowledge gained through the work is effectively transferred to other sugar industries outside of Southeast Brazil, including the Northeast Brazilian industry and industries in other developing countries. One possibility would be to hold a workshop (2 or 3 weeks long?) at the end of the project to review all industrial and agronomic findings with individuals invited from a number of different cane growing countries. Some GEF funds should be provided to augment the costs of putting on this workshop, but attendees should be required to cover some, if not all, of their travel and per-diem costs.MONITORING AND EVALUATION OF THE PROJECT 13. Aside from regular reporting on progress, there appears to be no other significant monitoring or evaluation activities included in the proposal. A mid-project, independent expert review would probably be beneficial, both to provide guidance to the project and to insure accountability. An independent project evaluation after completion might also be useful to understand the successes and failures of the overall approach for use in the design of future projects.JUSTIFICATION OF THE PROJECT IN TERMS OF GLOBAL ENVIRONMENTAL BENEFITS TO BE ACHIEVED AND EXISTING NATIONAL ENERGY STRATEGIES 14. Bagasse and cane trash from sugarcane are essentially CO2-neutral energy sources, because the CO2 released in their use for energy is reabsorbed by new sugarcane growth. (Some fossil fuel is used in the production, harvest and transport of sugarcane to mills, but this is relatively small and is neglected in the following calculation.) Based on the year-2027 country-by-country electricity production potentials shown in Table 1, the annual CO2 emissions from fossil-fueled electricity production that could be displaced ranges from 0.86 billion tonnes CO2, assuming the displaced electricity would otherwise be produced in highly-efficient natural gas-fired combined cycles, up to 2 billion tonnes CO2, assuming coal-based electricity is displaced. To put these numbers in perspective, total global CO2 emissions from all sources are estimated to be about 7 billion tonnes today. In cane-growing countries where fossil fuels are imported, there could be a substantial increase in energy security accompanied by savings in foreign exchange spending through use of cane power.GENERAL CONCORDANCE OF PROJECT OBJECTIVES, ACTIVITIES, OUTPUTS, BUDGET AND IMPLEMENTATION AND EXECUTION ARRANGEMENTS 15. Overall, the project is well conceived. The activities are well chosen and their implementation is well designed to achieve the desired objectives. The outputs could be augmented slightly to improve the value of the project to regions outside of Southeast Brazil and project monitoring and evaluation should be added to the proposal. The budget appears reasonable, and it includes conditional items that may not need to be pursued, depending on the decisions made at well-defined branch points in the project. The project management structure--especially the close coordination with the WBP project--makes very good sense.CALCULATION OR ANALYSIS OF INCREMENTAL COSTS TO BE FINANCED BY THE GEF TO ACHIEVE THE GLOBAL BENEFITS SPECIFIED IN THE PROPOSAL 16. From the GEF perspective, the primary global benefit that would ultimately be achieved if the project is successful would be reductions in CO2 emissions through displacement of fossil fuel for electricity production by electricity produced from CO2-neutral sugarcane residues. It is difficult to assign a CO2 emissions credit to this specific project, but it is clear that a successful project would do much to catalyze the implementation of BIG/GT systems in sugarcane processing facilities worldwide. At a minimum, a successful project would catalyze the implementation of BIG/GT systems in Brazil--the largest producer of sugarcane in the world, accounting for about 30% of the global total in the late 1980s. For the purpose of calculating a cost of saved CO2, two scenarios are considered. 17. In the first case, assume that the project leads to the startup in the year 2000 of one BIG/GT cogeneration plant at a facility processing one million tonnes of cane annually in Brazil. The facility would produce 430 GWh/yr of electricity in excess of that needed to operate the factory (see proposal, page 32). The carbon emissions saved (in thousands of tonnes of CO2) in the first year, assuming coal, oil or natural gas were displaced, would be 412, 325, or 177, respectively. Over a twenty-year plant lifetime, the total discounted CO2 savings (assuming a social discount rate of 3%) would be 6130, 4835, or 2633 tonnes. If the entire cost of the proposed work ($3.1 million) were charged against these CO2 savings, the cost of saved CO2 would be low: $0.5/tCO2 ($1.8/tC), $0.6/tCO2 ($2.4/tC), or $1.2/tCO2 ($4.3/tC).18. It may be more appropriate to consider that the project would catalyze the implementation of a series of BIG/GT facilities. For the purpose of calculating an alternative cost of saved carbon to that calculated above, assume the project successfully catalyzes the installation of 10 BIG/GT cogeneration facilities in Brazil or somewhere else in the world in the year 2000 at mills processing 106 tonnes of cane annually. Each of these cogeneration facilities would produce 430 GWh/yr of electricity in excess of that needed to operate the factory. Furthermore, assume that the growth rate in the implementation of new BIG/GT facilities averages, say, 10% per year from 2000 to 2027. This would result in a total BIG/GT power generation of some 64,000 GWh in 2027. This is about 10% of the total potential cane power calculated for Brazil in Table 1 or 3% of the global potential.19. Assuming the cane power displaces fossil fuel power, the discounted carbon emission savings, assuming a social discount rate of 3% per year, would be 318 million tonnes if coal were displaced, 250 million tonnes if oil were displaced, and 136 million tonnes if natural gas were displaced. If the entire cost of the proposed work ($3.1 million) were charged against these CO2 savings alone, the cost per tonne of CO2 saved would be extremely low: $0.010 if coal were displaced, $0.12 if oil were displaced, and $0.023 if natural gas were displaced. Per tonne of carbon saved, these costs would be 3.6 cents for coal, 4.5 cents for oil, and 8.4 cents for natural gas. BIOMASS POWER GENERATION: SUGAR CANE BAGASSE AND TRASH Concerns of the CEO of the GEF with proceeding with Brazil bagasse projectSUMMARY1. The two reasons indicated by the CEO of the GEF (in his memo of Dec. 22, 1994 to Ian Johnson) for deferring the Brazil bagasse project are (i) to await clear documentation on lessons learned from comparable projectsspecifically, "comparable initiatives in Brazil, Mauritius, and India" (memo of Dec. 20, 1994 to ElAshry from Ian Johnson); and (ii) to await clarification on whether the longterm operational strategy for climate change supports further activities in this type of biomass power generation.2. Regarding the first reason, to my knowledge there are no "comparable initiatives" currently ongoing or planned in Brazil, although there is obviously complementarity with the GEF biomass gasifier/gas turbine (BIG/GT) commercial demonstration project in Brazilin fact, the bagasse project is by design a complement to the BIG/GT project. As for the Mauritius and India activities, I presume these refer to the GEF projects that have already been approved, but which are still at early stages of implementation. I have reviewed the description of the India project given in the July 1994 GEF Chairman's Report (Part Two), and I have reviewed the February 1992 Project Document for the Mauritius Sugar Bioenergy Technology project. For reasons I elaborate below, it would seem that there is little that the Brazil bagasse project would learn by waiting for progress in either of these projects. There is some potential overlap only with one of the activities in the Mauritius project, but the Brazil project is already considerably further advanced in this particular area. This is the case because Mauritius has had some delays in its project, while Copersucar (the organization that will carry out the Brazilian project) has expended its own resources (up to the limit specified in the bagasse proposal) to progress this far.3. While there is no significant overlap among the India, Mauritius, and Brazil projects, there is some nice complementarity among them, which would argue for pursuing them in parallel: the India project targets institutional innovation to encourage biomassbased cogeneration in sugar mills with existing technology, the Mauritius project seeks primarily to demonstrate various commerciallyavailable technology options for increasing electricity production from sugarcane residues, and the Brazil project seeks to speed the commercialization of advanced (gasificationbased) cogeneration systems (using bagasse and sugarcane residues as fuel) that promise significant technical and economic improvements over existing commercial cogeneration systems.4. On the issue of gasificationbased power generation as an activity in the GEF's longterm operational strategy for climate change, it is worth noting that privatesector energy industries (including the Shell International Petroleum Company) are beginning to recognize the potential technical and economic attractiveness of such advanced biomass energy systems and the large potential markets that exist in developing countries. The generally good public relations generated by a company's involvement with the technology (due to its greenhouse friendly nature) is also an attraction. While the private sector is growing increasingly interested because of potential commercial and public relations returns, continued publicsector support of the commercialization of advanced biomass energy systems is warranted to insure that the technology is commercialized as rapidly as possible. Also, publicsector support is warranted because of the potential contributions that modernized biomass energy systems could make to sustainable development, especially in rural areas, where most biomass energy industries will be established.5. While there do not appear to be grounds for delaying the Brazil bagasse project to wait for results from India and Mauritius or for clarification on the operational strategy, there are some good reasons for proceeding without delay. As explained below, a further delay would mean at least 12 months before some key aspects of the project could be pursued (due to the requirement of synchronizing with the harvest season). Isaias Macedo, Technology Manager at Copersucar, estimates that such a delay would likely lead to at least a 30% increase in the overall cost of the project. Perhaps as importantly, the momentum that is being generated in the BIG/GT project and through the advance work by Copersucar on the bagasse project would be difficult to fully regain.6. Even more significantly, the private sector would be delayed in commercially tapping the benefits of gasifier/gas turbine systems using sugarcane residues as fuel [1]. Since cogeneration at sugar mills is attracting privatesector interest at a rapidly growing rate in Brazil and a number of other countries, increasing amounts of private capital are likely to be invested in cogeneration systems in the coming years. Demonstrating the promise of a new technology (BIG/GT) that is more efficient and economical than conventional systems (steam turbines) in sugar factory applications may be important in redirecting capital investments. Once investments are made in conventional systems, the capital will be locked up for 20 years or more.INDIA AND MAURITIUS PROJECTS7. India. The emphasis in the India project is on facilitating institutional innovation for the purpose of encouraging expanded implementation of conventional (boiler/steam turbine) cogeneration technology in sugar mills. While the use of sugarcane tops and leaves (trash) as a supplemental fuel to bagasse is mentioned, the systematic development of new technology for collecting and utilizing tops and leaves for gasification is not included in the project description. Rather, the project is ... designed to address the major market, financial and institutional obstacles to the introduction of these [already commercially available, but not widely used in India, cogeneration and biomass fuel supply] technologies and thereby demonstrate their competitiveness with other sources. (p. 72 in Chairman's report, with emphasis and parenthetical comment added.) ... The innovation in this project includes the development of institutional and technical capacity in India to help transfer, demonstrate, and commercialize advanced energy efficiency and renewable energy options for power generation. The project will feature state of the art efficiency techniques and monitoring activities as well as innovative institutional approaches, including those in marketbased operation and management practices, integration of marketbased and regulatory approaches to monitoring and enforcement, and financing options for new technologies. (p. 68, emphasis added)8. Thus, it seems that there is little or no overlap between the Brazil and India projects. (All of the effort in the Brazil project is aimed at new technology development to facilitate the commercialization of gasifier/gas turbine cogeneration systems for sugar mill applications.) On the other hand, there is some complementarity between the two projects. The institutional innovations that will be pioneered in India could provide some guidelines for other countries in establishing electricity exports from sugar mills. The India project could only provide broad guidelines, however, because of differences among countries in institutional structures, cultures, etc. Furthermore, it is not apparent that there would be major new lessons that Brazil could learn because Brazil has already been pursuing some major institutional innovations in the area of electricity sales by private sugarcane processors [2].9. Mauritius. The Mauritius project involves several distinct activities. Only one of these, the development or local adaptation of technologies for handling and processing sugar cane tops and leaves, is potentially relevant to the Brazilian project. As in the India project (and unlike the Brazilian project), the Mauritius project is targeting the use of tops and leaves in conventional (boiler/steam turbine) cogeneration systems.10. Sugarcane in Mauritius, as in most of the world including Brazil, is typically burned on the field before harvest. Burnt cane retains its sugar, but is much easier to harvest (especially manually) than is whole green cane. In the Mauritius project, the infield experiment stage includes assessing the mechanical and/or manual cutting of whole green cane (i) that is then transported to the factory where tops and leaves are separated from the stalk for use as a boiler fuel and (ii) the tops and leaves of which are separated from the stalk at the time of cutting and separately collected and transported to the factory. (See p.15 of Project Document.) It is not clear how far Mauritius has progressed to date with this part of the project.11. Despite the CEO's suggestion that the Brazil project be delayed until lessons from Mauritius are documented, it appears that the Brazilian project is already "ahead" of the Mauritius project in this area of potential overlap. Anticipating matching GEF funds, Copersucar has already progressed in the area of mechanized harvesting [3] and millside residue separation from the stalk (as described in their proposal) up to the limit of their specified cofinancing. In particular, they have expended some $1.4 million of their own resources to design, build, and test during the 1994 harvest season (May Nov.) a commercialscale (250 tonnes/hour) "dry cleaning" station for separating residues from stalk (see Fig. 2 showing three photos of the cleaning station in operation). This unit was designed to process burnt cane, which was also the feedstock used in the tests. The experience has provided the data needed for making the modifications to use the system on whole green cane. Copersucar is anticipating the use of GEF funds to pay for the design, engineering, and testing of the needed modifications.12. In November of 1994, Copersucar received a request from the Mauritius Sugar Authority for a proposal to design "a pilot plant for dry cane cleaning" for use in the Mauritius GEF project. Clearly, at least in the area of drycleaning of cane, the Brazil project does not stand to benefit from awaiting results from Mauritius. (In fact, Mauritius may stand to learn from the Brazil project!) In any case, it would be desirable for Mauritius and Brazil to independently pursue the development of cane cleaning technology, as good ideas are likely to emerge from both efforts.13. Copersucar has also already designed, built, and tested for one season (with burnt cane) a tworow mechanical harvester (at a cost in excess of $0.6 million) as proposed to the GEF. (See Fig. 3 showing three photos of the prototype harvester in operation.) GEF funds would cover the redesign, manufacture and testing of the harvester on whole green cane. (Mauritius has not proposed any new technology development relating to harvesters.)14. If GEF funds are not forthcoming, Copersucar plans to further develop both the harvester and dry cleaning station for use with burnt (not whole green) cane, because of the attractive economic potential they see in this. The work on whole green cane would not proceed. This would be a major setback to the development of the use of sugarcane tops and leaves for energy.15. Some other aspects of the Mauritius project could generate important experience to complement the Brazil project, but will provide no direct lessons for the Brazilians. For example, the bagasse transport technology study (see page 19 of Project Document), which is unrelated to any activity in the Brazil project, may have relevance for many countries. Also, valuable experience would be gained in institutional and other aspects of yearround operation of a sugar mill power plant through use of bagasse (during harvest season) and coal (during offseason) as proposed for Mauritius.BIOMASS AS PART OF AN OPERATIONAL STRATEGY FOR CLIMATE CHANGE16. An indication of the likelihood that modernized biomass energy will play an important role in the world's future is reflected in the changing thinking on biomass among conventional energy industries. One of the clearest illustrations of the trend is the most recent analysis published by the Group Planning Division at the Shell International Petroleum Company. (Analyses of the Group Planning Division provide input for longterm decisionmaking within the Royal Dutch/Shell group of companies worldwide.) In Shell's "New Frontiers" scenario, where economic growth and energy demand growth are both assumed to be strong, Shell shows rapid development of a renewable energy industry beginning late this decade. By 2050, renewables account for nearly half of total global energy supply, with biomass accounting for over onethird of the renewables (Fig. 1). The market implications of this analysis may be one of the primary reasons that the Shell International Petroleum Company and its affiliate, Shell Brasil, are so actively engaged in the Brazilian BIG/GT demonstration, including committing $5 million of investment capital toward construction of the facility.17. There are several good arguments as to why biomass, when used in advanced conversion technologies like the BIG/GT, is very likely to play as important a role as envisioned in the Shell scenario, especially in a future greenhouseconstrained world. (a) Because sustainably produced biomass absorbs CO2 as it grows and releases an equivalent amount when it is used for energy, biomass is a carbonneutral energy resource. If sustainable biomass energy replaces fossil fuel use, overall carbon emissions would be reduced. (b) A number of studies have concluded that commercialized versions of advanced biomassenergy technologies like BIG/GT could be economically competitive with fossil fuels. This is especially true in applications where the biomass cost is relatively low, as it would be for sugarcane residues. There are many such potential applications worldwide. For example, over 80 developing countries grow sugarcane. (c) It has been widely argued that biomass energy has the potential for making important contributions toward sustainable development. Since biomass production is an inherently rural activity, rural employment opportunities would be generated, energy inputs to agriculture might be increased, and energyusing industries (and associated economic activities) might be drawn to rural areas.18. Given the prospective commercial viability of advanced biomass energy technologies, together with the carbonneutrality of sustainable biomass energy, and the opportunities modernized bioenergy might provide for sustainable development, publicsector support needed to help realize the implementation of such modernized bioenergy systems is highly warranted. Despite the strong privatesector interest in the application of commercialized BIG/GT technology, publicsector sharing of the development costs is needed to leverage private sector willingness to invest at this precommercial stage in the technology development process.COSTS OF DELAYING THE BRAZIL PROJECT19. The Brazil bagasse project was designed as an extension of the BIG/GT demonstration project and has the following three main objectives: (i) to develop green cane harvesting and processing technologies that would make sugarcane tops and leaves (trash) available for gasification at a sugar mill at minimum cost, (ii) to test the gasification of bagasse and trash in the furthest developed of atmospheric and pressurized gasification systems, and (iii) to develop engineering studies of the "best options" for integrating biomassgasifier/gas turbine cogeneration systems into sugar mills. With a delay in the approval of the GEF grant, there would be considerable risk that the cost associated with achieving each of these objectives would increase significantly: (a) As described above, Copersucar has already invested considerable resources of their own ($2 million or more) in launching the work proposed for GEF support. In particular, they have designed, built and tested for one season (with burnt cane, and some small preliminary trials with green cane) a tworow mechanical harvester and a 250 tonne/hour cane drycleaning station. Enough data has now been collected to enable redesign for green cane. Copersucar is anticipating GEF support to pay for the redesign and testing on green cane. Copersucar has been planning to test the re designed units during the 1995 cane crushing season (May November). With a delay in GEF approval, it is conceivable that the redesign and re building work would not be completed in time for any testing during 1995, in which case testing could not begin until May 1996 a 12 month delay. (b) The cost consequences of such a delay are potentially serious for the development of the drycleaning technology. The 250 t/hour unit that Copersucar has already built is capable of handling the entire capacity of the mill (Acucareira Quata) where it is installed. It is installed in parallel with the existing system that it will eventually replace. Both systems were operated during the 1994 crushing season, and the mill owners have agreed to parallel operation again during the 1995 season. In 1996, the mill plans to adopt the drycleaning station for commercial operation and retire its existing system. (Only a few tests are planned for 1996 as part of the GEF project.) (c) A one year delay in the drycleaning tests would mean that Acucareira Quata will have commercially adopted the drycleaning unit, which would make it difficult to run tests with sufficient flexibility to get good results over the originally planned duration of testing. In all likelihood, an additional year of testing would be needed to complete all of the tests without excessively disturbing the Acucareira Quata commercial operation. (The strain this might place on the good will of the Acucareira Quata personnel would not make it any easier to complete the work.) There would also be added costs of maintaining the drycleaning station during the 1995 season. (d) In the extreme situation, another drycleaning station would need to be built (at a cost of no less than $1.2 million), and the delay would be still greater. (e) There are similar potential cost consequences for the development of the harvester. Without the modifications for green cane harvesting, which Copersucar would pay for with GEF funds, precommercial testing of the unit would continue on burnt cane during the 1995 season. This would be followed in 1996 by final development of a commercial unit for burnt cane harvesting (with selected commercial manufacturers). At that point, it would be difficult to use the harvester for green cutting trials (after it had been developed for commercial use with burnt cane). (Making the needed modifications would be more difficult.) In all likelihood, another prototype would need to be built for green cane testing, at a cost of several hundred thousand dollars. (f) Finally, in anticipation of GEF funding being approved, Copersucar has already scheduled many of the proposed agronomic tests (trash use for herbicide elimination, trash baling test, etc.). The testing will involve a large number experiments with different equipment at 10 different sugar mills. All tests have already been programmed. A delay will force a re organization and, in some cases, carrying out of additional tests to those originally planned. The overall result would likely be an increase in costs, and a loss of interest from the 10 cooperating mills, making it more difficult to conduct the tests. (g) When the Brazil bagasse project was originally proposed in 1993, it included a schedule for gasification tests that was synchronized with related activities in the GEF's Brazilian biomass gasifier/gas turbine (BIG/GT) demonstration project. In particular, the original bagasse proposal called for gasification testing in 1994. Until now, some delays in the BIG/GT project have allowed ready accommodation of the delay in GEF approval of the bagasse project. If the bagasse project were to go ahead at this point, it would still be in sync with the BIG/GT project. (h) A further delay in approval, however, would create some disruptions in the schedules for gasification testing that could result in higher costs for the gasification tests. As you know, there are presently two gasifier developers (TPS and Bioflow) competing for the right to proceed to phase III in the BIG/GT project. TPS (atmospheric pressure gasifier) completed all of their gasification tests for the BIG/GT project late in 1994. A delay in approval of the bagasse project would mean a large time gap in further testing, which would involve a loss of momentum and a monetary cost in TPS participation. TPS proposed to carry out work for the bagasse project on the assumption that it would follow on directly after (or partly overlap with) the work TPS has been doing for the BIG/GT project. Since TPS is a small company, a time gap between the two projects will probably mean that the team assembled to do the BIG/GT work would need to be dispersed and the pilot gasifier facility would need to be temporarily mothballed. Once the team is reassembled, some engineering design work would probably need to repeated, and the test facility would need to be recommissioned. Obviously, more time would be needed (than originally proposed) to accomplish the work, and it would probably be more costly (perhaps a few hundred thousand dollars more costly) [4]. This would be especially the case if TPS is not selected as the Phase III gasifier supplier, because then TPS would be decoupled from the BIG/GT project altogether. (i) There would probably be less of a momentum loss with Bioflow (pressurized gasifier/gas turbine) because work is ongoing in any case at the Varnamo pilot demonstration BIG/GT facility in Sweden. Nevertheless, the Bioflow people have been indicating all along to Copersucar that there was some uncertainty as to whether a window of opportunity could be identified for testing bagasse at Varnamo. This uncertainty appears to be growing as time passes. Because Bioflow has prior commercial commitments to sell electricity from the Varnamo plant, and because the testing and demonstration phase at Varnamo has taken longer than anticipated [5], Bioflow has been delayed in meeting its commercial obligations. Bioflow will not want to delay fulfilling their commitments any more than absolutely necessary. (j) The costs indicated in the Copersucar proposal for the system integration studies are based on quotes from the Scandinavian gasifier suppliers that reflect the fact that they were planning on using the experience gained in the BIG/GT testing and evaluation phase. If the BIG/GT and bagasse projects are decoupled in time, there would inevitably need to be some repetition of work, which would lead to higher costs and a longer time to complete the work. (k) The analysis in this section of my memo is based on communications I have had with Isaias de Carvalho Macedo, Manager for Technology at the Copersucar Technology Center and the person most familiar with the proposed bagasse project. His overall estimate is that at least a 30% increase in overall cost of the project is likely with a further delay in GEF approval. (l) However, there would be a much larger, though difficult to quantify, economic loss as a result of the delay in commercial application of the technologies that would be developed in the project. The export of cogenerated electricity from sugar mills as a business venture appears finally to be gaining momentum in Brazil and a growing number of other countries; the promise of a new technology (BIG/GT) that is more efficient and economical than existing commercial options may be important in re directing capital investments. Once an investment is made in a cogeneration system, the capital is locked up for 20 years or more. This could considerably delay the introduction of BIG/GT cogeneration systems at sugarcane processing facilities.NOTES:1. It is clear to me that the BIG/GT technology fueled by woody biomass will be commercially demonstrated within a couple of yearsthere are some 10 or 12 projects ongoing worldwide with this objective. While I see no fundamental obstacles to running BIG/GT systems on sugarcane residues, the type of work proposed in the Brazil bagasse project is needed to help identify modifications needed in the areas of fuel supply, residue gasification, and overall integration with the rest of the sugarcane processing facility.2. For example, Sao Paulo (Brazil's largest cane producing state) has now in place legislation requiring utilities to purchase cogenerated power from sugar mills at a fair price. This legislation is akin to the Public Utilities Regulatory Policy ActPURPAthat was enacted in 1978 in the U.S. and led to a rapid increase in the early 1980s in the sale of privately cogenerated electricity to utilities.3. Copersucar does not consider manual harvesting of whole cane as a realistic largescale option for the future in Brazil, and so is not considering this possibility in its work. The need to improve the living and working conditions of field laborers rules out the possibility of employing the enormous amounts of lowpaid labor that would be needed for economical manual harvesting of green cane and recovery of trash. Even today, with burnt cane, mechanical harvesting is growing steadily in Brazil because of lower costs; it leads to fewer jobs, but much higher paying jobs.4. This is a guesstimate.5. Bioflow originally set a very aggressive design, construction, testing and demonstration schedule. In essence, they set out to build and run a new, unproven technology on the same schedule as a commerciallymature technology. In retrospect, this was overly ambitious. However, it now appears that most of the problems encountered in the process have been identified and solved, so that the demonstration will, ultimately, be successful.


WORK PROGRAM PROPOSED FOR COUNCIL APPROVAL